Engineering Projects
Case studies and project highlights from our consulting work.

Surge Analysis of a Fibreglass Firewater Ring Main
GRE Firewater Network and Pump Start Sequence A grassroots methanol plant distributes firewater through a fibreglass (GRE) ring main serving all units and the common facilities. Aboveground piping at the flare stack area and fire training ground was assumed to be steel. The firewater pumps draw from a firewater pond

Design Review of a Shared LNG Terminal and Power Plant Seawater System
Shared Seawater Intake for an LNG Terminal and a CCGT Plant The IONIO project comprises a new LNG regasification terminal in an industrial area that also hosts the ERG power station, a combined-cycle gas turbine (CCGT) plant. Both facilities need seawater. The terminal uses it to vaporise LNG, while the

Nozzle Load Feasibility Analysis for Floating LNG Compressor Piping
Wind, Barge Motion and API 617 Limits on Large-Bore Compressor Piping On a floating LNG (FLNG) platform, natural gas is compressed in a module installed near the centre of the barge. Four large-bore lines connect to that compressor: a 52-inch low-pressure suction line, a 36-inch medium-pressure suction line, a 30-inch

GRE Firewater Ring Main Surge Analysis and Air Valve Protection
Firewater ring main and surge analysis scope A firewater system was specified for a new platform, to be connected to the firewater systems of the two existing platforms it extends. The system is a wet ring main: permanently water filled and held under pressure by a jockey pump on one

Surge and Dynamic Stress Analysis of an Offshore Seawater Cooling System
Water hammer on a sister platform and the GRE seawater system The seawater system on a 690 MW offshore converter station provides seawater for cooling. During testing of the seawater system on a sister platform, water hammer effects were observed during an emergency shutdown of the seawater lift pumps, and

Waterhammer Root-Cause Analysis for Offshore Seawater Cooling
Pipework Displacement During a Seawater Lift Pump ESD During commissioning of the seawater cooling system at an offshore HVDC substation, an emergency shutdown (ESD) of the seawater lift pump produced uncontrolled displacement of the connected 12-inch glass-reinforced epoxy (GRE) pipework. Video of the test showed an estimated 18 mm of

Surge Analysis of Offshore Monopile Deluge Fire Water Systems
Deluge Piping Configurations and Upset Scenarios Deluge fire water systems had been installed on three offshore monopiles. A surge (waterhammer) analysis was carried out for two purposes. The first was to determine the maximum pressure in each system and the unbalanced forces to be accommodated by the support system. The

Slug and Hammer Analysis of HIPPS Valve Closure on a 16-inch/12-inch Gas Riser Line
Slug Impact on a Closing HIPPS Valve A 16-inch steel gas riser lands on a platform, and a 12-inch line branches off the riser into the platform. A HIPPS valve on the 12-inch branch protects the downstream platform from pressures exceeding 150 Barg. The 16-inch riser is exposed to slug

Pressure Thrust and Surge Loads on a DN600 GRE Seawater Header
GRE Header Design Conditions and Material Properties An above-ground seawater header in glass-fibre reinforced epoxy (GRE) supplies seawater to a process unit through two tie-ins on a seawater pump discharge manifold. The analysis assessed the static stresses in the header and defined a support arrangement that supports and stabilises the

Pipe Stress Analysis of a Prefabricated DN800 GRE Seawater Spool With an Untied Bellow
Bellow Overextension in a DN800 GRE Seawater Spool A DN800 spool in glass-fibre reinforced epoxy (GRE) was to be installed to transport seawater. The GRE material has unequal axial and hoop stiffness, with an axial elastic modulus of 10,500 MPa and a hoop elastic modulus of 20,500 MPa. Its “effective”

Stress Analysis of a 56-Inch GRE Seawater Dump Caisson
Caisson Configuration and Client-Specified Loads A seawater dump caisson is mounted on a deck of an offshore structure. It consists of a 56-inch (ID1400) GRE pipe header, EST series with a 55° winding angle, fixed at the main deck and guided at the upper deck. At the top section, two

Thermal Stress Analysis of Stainless Steel Support Rings and a Partition Plate in a Carbon Steel Claus Reactor
Dynaflow ran a finite element analysis to ASME VIII Division 2 of a stainless steel SA240 316L support ring welded into a carbon steel Claus reactor. All primary stresses were within the allowable. At the head-to-ring connection, however, secondary stress reached 885 MPa (259 percent of the allowable), and fatigue

Finite Element Stress Assessment of Two Sulphur Recovery Condensers
Two identical condensers cool sulphur gas to a temperature close to its dew point. The gas passes through 363 SA-179 tubes of 38.1 mm outside diameter and 8840 mm straight length, set on a 48 mm triangular pitch between two stationary tube sheets. On the shell side, water maintains a

Stress Analysis of Underground GRE Firewater Piping at a Main Degassing Station
New water hydrants were installed as part of an upgrade of the firewater system at a main degassing station. Each hydrant valve joins the steel hydrant part to the underground glass-reinforced epoxy (GRE) piping, and the GRE piping connects to steel piping coming from the above-ground equipment. The GRE is

Dynamic Stress Analysis of Steam Relief Valve Piping
Firing of three relief valves on a steam line operating at 225 °C and 9.5 barg was analysed in CAESAR II, with dynamic loads generated in BOSfluids. The spectrum analysis gave a combined dynamic and static stress of 128% of the occasional allowable stress and the time-history analysis including the

Slug Load and Steam Hammer Analysis of a 36-inch High-Pressure Steam Line at Cold Start-up
Condensation and Steam Hammer in a Cold Steam Line The analyses assumed steam at 380°C and 40 Barg entering a 36-inch high-pressure steam line with a pipe temperature of +5°C. Potential problems are anticipated at start-up because the steam condenses on entering the cold pipe. Steam remaining in the line

Transient Slug and Surge Analysis of a 12-Inch Steam Start-Up Line
A BOSfluids surge analysis and slug impact calculation of a 12-inch steam start-up line gave maximum unbalanced forces of 1.32 kN, 1.3 kN and 3.2 kN for three surge scenarios, and 16.5 kN and 23 kN for 7 m and 10 m slug impacts on the pressure control valve. CAESAR

Pipe Stress Analysis of a Sales Gas Compressor Discharge Line
During re-alignment of the suction and discharge piping for sales gas compressors K2002A and K2002B, ready for connection to the compressor nozzles, the discharge line of K2002B could not be correctly aligned. The displacement at constant load hanger 04-SS-1017 (PS 1017) took the hanger out of its operating range. A

Stress Analysis of a Revised High-Pressure Blowdown Line Connection
A CAESAR II stress analysis of a revised high-pressure blowdown line operating at 20.6 barg and 160 °C found that the system as proposed did not meet ASME B31.3 because of large thermal displacements of the DN600 header. If guide support S1 is replaced by a restraint in the z-direction

Steam Turbine Exhaust Piping Stress Analysis to NEMA SM 23
At a refinery, instrument air is supplied by three Atlas Copco compressors. Two are motor driven; the third is driven by a Coppus RHLA-24 steam turbine commissioned in 2008. Two months after start-up, a plain bearing malfunctioned. The turbine was overhauled and reassembled at site in August 2009, after which

Pump-Trip Fatigue Analysis of a Circulation Water Weld Crack
Weld 34 Crack and Dead-End Configuration The circulation system has two pumps, one operating and one spare. The operating pump feeds cooling water back into the Benson vessel at the top of the system. In the situation analysed, one pump had been taken out for revision. A blind valve was