Engineering Projects
Case studies and project highlights from our consulting work.

Stress Analysis of a Flue-Gas Overhead Line Operating in the 304H Creep Range
A flue-gas overhead line runs from a third stage separator to a waste heat boiler. It carries gas at a maximum operating temperature of 740 °C upstream of the orifice chamber and is designed for 755 °C in the hot-walled sections. At those temperatures the hot-wall material, stainless steel A240

Flexibility Analysis of a GRE Cooling Water Header Replacement
Two existing steel cooling water headers were to be replaced with Glass Reinforced Epoxy (GRE) piping under two Technical Change Requests. This case study covers the first request, for the main cooling water header “boiler”. The second, covers the “lube” header. A flexibility analysis was required, together with recommendations, to

Slug-Flow Vibration Assessment of an 8-Inch Two-Phase Refinery Line
An 8-inch line carrying two-phase content from a heat exchanger to a gasoil stripper at a refinery had been vibrating for years, mainly in the two shorter horizontal sections, one downstream of the heat exchanger and one just upstream of the stripper. The operator had reported vibration for 5 to

High Temperature Stress Analysis of an FCC Fluegas Overhead Line
A line in the creep range, where the weight loads set the support design The line studied here is the revised fluegas overhead line between the third stage separator and the superheater. It operates at 725 °C in the hot walled sections and 200 °C in the cold walled section,

Flexibility Analysis of a Stainless Steel Radiant Coil Replacement at 650 °C
A coil anchored at both ends, with the cross-over overloaded In a refinery furnace, the radiant coil carries crude. Under a project designated high TAN, the existing carbon steel radiant coil piping is to be replaced by stainless steel, grade A312 TP316Ti. This account presents the stress analysis of the

Reducing Slug-Induced Vibration on Four Two-Phase Hydrofiner Lines
Lines assessed 4 Pipe content Two-phase gas-liquid flow, all process conditions Flow regime, start-up Slug flow Flow regime, normal operation Annular flow Pipe material A 358 type 321, main material Design temperature 400 °C Design pressure 77.5 bar, Lines 1 and 3; 81.0 bar, Lines 2 and 4 Liquid slug

Replacing an Expansion Joint with an Expansion Loop on a 700 °C Catalyst Withdrawal Line
Line temperature 700 °C Design temperature 755 °C Design pressure 4.2 barg Pipe material A 312 type 304H Allowable stresses ASME B31.3 Appendix A Expansion loop 4 inch, 6,000 mm deep Creep-range service on the catalyst withdrawal line A waste catalyst line runs from the regenerator to the waste catalyst

Mitigating Vibration-Induced Fatigue in Hydrogen Compressor Branches
Recently, fatigue cracks were discovered in the first-stage discharge line’s small-bore instrumentation branches of a hydrogen compressor. Initial investigations pointed to excessive out-of-plane vibrations as the primary driver of these failures. While the system was originally installed in 1995 with a pulsation study, and further axial supporting was added in

Optimizing Effluent Piping Design for High Differential Settlement Introduction
In industrial effluent systems, piping integrity is often threatened by the geotechnical behavior of the surrounding soil. This case study examines the peer review of a stress analysis for effluent pipelines situated between valve chambers. The primary challenge identified is differential settlement, where unpiled concrete pit walls shift relative to

Finite Element Analysis and Verification of Actuator Type F35-340
Introduction This case study presents the finite element analysis (FEA) and verification process conducted for the pressure-containing parts of the F35-340 actuator, developed by Actuator Technology Company. The primary goal was to demonstrate the structural integrity of the actuator under specified operating conditions and to ensure compliance with the requirements

Fatigue Assessment of the 28L Oil Separator
This case study presents the fatigue assessment of the 28L oil separator (Atlas part number 1625481501), performed to verify the vessel’s durability under cyclical internal pressure in accordance with the AD2000 S2 standard. The separator is subject to a cyclic pressure loading from atmospheric pressure up to 15 barg, which

Root Cause Analysis of Vibrating Regulator Valve 670FC005-VC
This project examines the root cause of increased vibrations observed in the control valve 670FC005-VC at Shell Pernis following its replacement with a new valve from a different manufacturer. The resulting vibrations led to a critical mechanical failure at the connection between the valve stem and the actuator. The objectives

Surge and Dynamic Stress Analysis of Foam Line AFW-023024
At BP Geel, a new extension of the fire protection system experienced operational failures during start-up due to surge effects. A similar incident with line AFW-023025 had previously prompted a surge analysis, leading to the current study focused on the adjacent foam system, line AFW-023024. The foam line, running nearly

Dynamic Stress Analysis of Foam Line AFW-023024
At the BP Geel facility, a previous failure of the fire protection system during start-up prompted a detailed investigation into surge effects within the network. The incident occurred on line AFW-023025, and subsequent studies identified hydraulic transients as the primary cause. Given the similar configuration and operating principle of the

Vibration Review Using Modal Analysis and CFD for Yellowtail FPSO
The ONE GUYANA Floating Production Storage and Offloading (FPSO) unit has been designed to operate in deepwater conditions with a production capacity of 250,000 barrels of oil per day. The FPSO is designed for a 20-year operational life, handling complex processes including water and gas injection. Previous projects highlighted the

Evaluation of Wearplate Thickness for Pipe Supports on FPSO Maria Quiteria
During this project the optimal wearplate thickness for pipe supports on the FPSO Maria Quiteria was investigated, aligning with the Yinson project specifications. The primary objective was to validate whether the prescribed wearplate thicknesses—6mm for pipes of 10” and smaller, 10mm for larger pipes, and 12.7mm for pipes with higher

Root Cause Analysis and Flow Optimization for Goliat FPSO Minimum Flow Line
On the Goliat Floating Production Storage and Offloading (FPSO) unit, significant vibration and cavitation phenomena were observed downstream of control valve 71PV1103 on the minimum flow line of pump B during maximum flow conditions. Additionally, pressure surges were reported during system start-up through this minimum flow line. Such issues posed

Offloading Surge Analysis for Teekay Petrojarl I FPSO
The Petrojarl I Floating Production, Storage, and Offloading (FPSO) facility, in operation since 1986 in the North Sea, underwent critical modifications to prepare for deployment at the Atlanta oil field offshore Brazil. The relocation entailed adapting the crude oil offloading system to manage Brazilian crude with higher viscosity and to

Waste Water System Surge Analysis for Rotterdam NH3 Terminal
The client commissioned a surge analysis for the Waste Water (WW) system at the Rotterdam terminal. The analysis aimed to quantify transient pressures and unbalanced forces generated by various hydraulic events: pump trips, pump startups, pump switchovers, and the closure of two key butterfly valves. The analysis was performed using

Stress Analysis and Remediation of Tank Lines
This case study presents the findings of a comprehensive pipe stress analysis of several tank lines following a leakage incident at an expansion joint. The analysis was initiated after segments of the tank lines were replaced with new routing. Upon operation of the system, a leak was detected at the

Stress Analysis of FRP PVC-U Piping for Temporary SOx Filter Installation
The project focused on evaluating the mechanical integrity and support strategy of a glass-reinforced plastic (FRP) piping system lined with unplasticized polyvinyl chloride (PVC-U), designed to protect the glass-reinforced plastic structural layer against the corrosive gas mixture. The temporary installation provides an additional gas cleaning stage for the sulphuric acid