Surge Analysis of a Fibreglass Firewater Ring Main

ON THIS PAGE

GRE Firewater Network and Pump Start Sequence

A grassroots methanol plant distributes firewater through a fibreglass (GRE) ring main serving all units and the common facilities. Aboveground piping at the flare stack area and fire training ground was assumed to be steel. The firewater pumps draw from a firewater pond filled with re-mineralised desalinated water, and with seawater in an emergency.

The installed GRE pipe is rated for a long term pressure of 16 barg, with a short term allowable of 1.4 times that rating, 22.4 barg. The surge study set out to find the highest and lowest pressures in the network, and whether a surge drum, vacuum breakers or pressure relief devices were needed to keep overpressure and vacuum within the pipe allowable values.

Two jockey pumps keep the ring main pressurised at 9 barg. The first starts when pressure falls below 8.5 barg and stops at 9 barg, and the second takes over if the first fails. Three main pumps follow in stages. If pressure falls below 8.0 barg and does not recover within 10 seconds, the first diesel driven main pump starts. Below 7.5 barg without recovery within 30 seconds, the second diesel driven main pump starts, and below 7.0 barg without recovery within 50 seconds, the electric motor driven main pump starts. The surge model included this start logic.

Pump Start-up and Hydrant Closure as the Critical Cases

Several upset conditions were simulated, and two were identified as the most critical. The first follows a fire alarm: hydrants open, ring main pressure falls and the pump start sequence begins. The second comes at the end of firefighting, when the open hydrants close while a main pump is running. Pump start-up was checked for both low and high pressures, and hydrant closure for high pressure.

The model included the twelve hydrants in the gas metering area, in three sets of four, because they are located furthest from the pump area.

Surge Model of the Ring Main in CAESAR II and BOSfluids

The ring main layout was built in CAESAR II from the firewater isometrics and piping plans, then imported into BOSfluids, where the pumps, the check valves at the pump discharges and the hydrant connections were added. Each hydrant was modelled with a capacity of 59.0 to 59.4 m³/hr.

Some inputs were conservative estimates or assumptions. Main pump inertia was a conservative low estimate, the main pump start-up time was assumed to be 5 seconds, and the water was modelled at 45°C with a conservative density.

Before the transient runs, a steady-state run with all gas metering area hydrants open and a main pump running was used to verify the model and check the flows. The flow through each hydrant conformed to the client’s specified minimum of 57 m³/hr at 7.0 barg.

The pump start-up case began with the network at 9.0 barg and the jockey supply isolated, after which all twelve hydrants opened together at one second per inch of diameter. The hydrant closure case began with a diesel driven main pump supplying the open hydrants, and all twelve then closed together at the same rate, for a total closure time of three seconds.

Surge model layout of the firewater ring main, with pipe diameters in mm shown by colour and the pump area, gas metering area, flare stack area and fire training ground labelled.
Surge model layout of the firewater ring main, with pipe diameters in mm shown by colour and the pump area, gas metering area, flare stack area and fire training ground labelled.

Minimum and Maximum Surge Pressures in the Ring Main

Pressure in the pump manifold fell through all four start thresholds within five seconds of the hydrants starting to open. The first jockey pump started but did not restore pressure above 8.0 barg within 10 seconds, so the first diesel driven main pump started. Pressure then recovered above 7.5 and 7.0 barg inside their 30 and 50 second windows, so the second diesel driven main pump and the electric motor driven main pump were not needed.

The lowest pressure in the firewater lines, 1.64 barg, occurred at a gas metering area hydrant while the hydrants were opening and before the main pump started, so there was no critical vacuum condition. Once the main pump was running, pressure at its discharge reached a maximum of 15.5 barg. The system reached a steady state after about 35 seconds, with 14.8 barg in the pump manifold. One main pump was sufficient for the hydrant demand modelled.

Hydrant closure gave a maximum pressure of 21.2 barg near one of the hydrant sets, within the 22.4 barg short term allowable.

Pressure at the main firewater pump discharge during pump start-up, rising after the pump starts to a maximum of 15.5 barg.

Surge Protection Requirements for the GRE Firewater Network

Both cases stayed within the allowable values for the piping without a surge drum, vacuum breakers or pressure relief devices, so no protective measures were required. These results were obtained with conservative inputs for main pump inertia and fluid density and an assumed main pump start-up time.

For the GRE pipe, peak pressures were checked against a short term allowable tied to its long term rating, 1.4 times 16 barg, and minimum pressures against vacuum. Simulating hydrant opening with the plant’s pump start logic, and hydrant closure against a running main pump, gave the minimum and maximum pressures for these checks and showed which pumps start as pressure falls.

Maximum pressure across the firewater ring main when all hydrants close together, with the highest values on the line to and around the gas metering area.

Frequently Asked Questions

What surge pressure does hydrant closure cause in a GRE firewater ring main?

In this ring main, closing all twelve hydrants together over three seconds, with a diesel driven main pump running, gave a maximum pressure of 21.2 barg near one of the hydrant sets. That is within the 22.4 barg short term allowable of the GRE pipe, so no protective measures were required.

In this network it did not. The lowest pressure in the firewater lines was 1.64 barg, at a gas metering area hydrant, while the hydrants were opening and before the main pump started, so there was no critical vacuum condition.

For this project, the GRE pipe is rated for a long term pressure of 16 barg, and its short term allowable is 1.4 times that rating, 22.4 barg. Peak surge pressures were checked against this value and minimum pressures against vacuum.

This one did not. Both critical cases, pump start-up and hydrant closure, stayed within the allowable values for the piping without a surge drum, vacuum breakers or pressure relief devices. The results were obtained with conservative inputs for main pump inertia and fluid density and an assumed main pump start-up time.

In the start-up case, the first jockey pump started but did not restore pressure above 8.0 barg within 10 seconds, so the first diesel driven main pump started. Pressure recovered inside the 30 and 50 second windows for the second diesel driven main pump and the electric motor driven main pump, so neither was needed, and one main pump was sufficient for the hydrant demand modelled.

Here the ring main layout was built in CAESAR II from the firewater isometrics and piping plans, then imported into BOSfluids, where the pumps, the check valves at the pump discharges and the hydrant connections were added for the transient runs.