News & Insights from Dynaflow Research Group

surge analysis, GRP, sea water system
Engineering Training

GRP Sea Water System

Introduction The seawater system was classified as a class A system per the Service Limit State (SLS) standards. Constructed from reinforced fiberglass piping, it comprised

Read More »
drilling rig, fiberglass, finite element analysis, fiberglass engineering
Fiberglass Engineering

Pump Lines On A Drilling Rig

Introduction In this case study, the focus was on conducting a stress analysis of the GRE piping system utilized to link the pumps to the

Read More »
Fiberglass Engineering

GRE Seawater Dump Cassion

Introduction In this case study, a finite element stress analysis was conducted on a seawater dump caisson installed on the deck of a floating offshore

Read More »
Uncategorized

Pulsations Paper

Benefit of computational simulation of a pulsation dampener compared to an analytical method Accumulators are used to reduce pressure pulsations from reciprocating pumps by adding

Read More »
CAESAR II 3D model of A106B piping into a flare seal drum, showing the expansion loop and support locations on the inlet line.

Pipe Stress Analysis of an Offshore Flare Seal Drum System

An Offshore Flare System Facing Wind, Thermal and Nozzle Load Constraints An offshore compressor station required a flexibility assessment of the piping running toward and from its flare seal drum (V-004). The work continued an earlier analysis of the same station’s flare system and covered the modified and continuation piping

Learn More »
Stress analysis model layout of the flare header with the PSV routing of the compressor stations.

Flexibility Analysis of an Offshore Flare Header to ASME B31.3

Offshore Flare System Loads and Flange Overstress An offshore compressor station system consists of five very similar compressor stations connected by one 42 inch header. The work covered the flare system of these compressor stations. The location requires wind loads with wind speeds of 240 km/h to be included, with

Learn More »

Surge and Stress Analysis of an Offshore GRE Firewater System

Firewater System Upgrade on Two Bridge-Connected Offshore Platforms As part of an offshore field development, the firewater networks on two bridge-connected platforms, referred to here as Platform A and Platform B, were upgraded. New glass-reinforced epoxy (GRE) piping was installed on both platforms and on the connecting bridge, with short

Learn More »

Surge Analysis of a Fibreglass Firewater Ring Main

GRE Firewater Network and Pump Start Sequence A grassroots methanol plant distributes firewater through a fibreglass (GRE) ring main serving all units and the common facilities. Aboveground piping at the flare stack area and fire training ground was assumed to be steel. The firewater pumps draw from a firewater pond

Learn More »

Waterhammer Root-Cause Analysis for Offshore Seawater Cooling

Pipework Displacement During a Seawater Lift Pump ESD During commissioning of the seawater cooling system at an offshore HVDC substation, an emergency shutdown (ESD) of the seawater lift pump produced uncontrolled displacement of the connected 12-inch glass-reinforced epoxy (GRE) pipework. Video of the test showed an estimated 18 mm of

Learn More »
Colour plot of maximum unbalanced forces in two-ring steel deluge piping after a firewater pump trip.

Surge Analysis of Offshore Monopile Deluge Fire Water Systems

Deluge Piping Configurations and Upset Scenarios Deluge fire water systems had been installed on three offshore monopiles. A surge (waterhammer) analysis was carried out for two purposes. The first was to determine the maximum pressure in each system and the unbalanced forces to be accommodated by the support system. The

Learn More »
CAESAR II model layout of a DN600 GRE seawater supply header, with steel discharge manifold sections at the left.

Pressure Thrust and Surge Loads on a DN600 GRE Seawater Header

GRE Header Design Conditions and Material Properties An above-ground seawater header in glass-fibre reinforced epoxy (GRE) supplies seawater to a process unit through two tie-ins on a seawater pump discharge manifold. The analysis assessed the static stresses in the header and defined a support arrangement that supports and stabilises the

Learn More »